                  47uf       47uf
                  50V         50V

                                        ZENER      >|
                                        DIODE
                                            >|          2K4 5W

                        15K         47K            >|


                      >|
                                                                                  50-50 uF  500V
                                                   >|
                              620K 1W
                              180K 1W
                                                                                 220K 2W
                                                               KT66    6V6

                                                                             HT1
                                                                  Bias



            Wire the bias switch to the Zener diode so that in one position, the two resistors are connected to
            two terminals (center and outside) and the 18V 5W zener diode to the other two (center and
            outside) of the DPDT toggle switch.  This is the 6V6 Position.
            .




            3 Install Transformers

            Install the power transformer.  The Power transformer lies down along it’s ‘long axis’. Tightly twist
            the AC mains leads (Black/Black) together. Braid the High voltage (Red - Red/Yellow - Red) and
            the heater leads (Green – Green/Yellow - Green).

            Align the AC mains leads so they face towards the outside of the chassis.  The High voltage (Red -
            Red/Yellow - Red) and heater leads (Green – Green/Yellow - Green) face inwards.   Feed the
            leads through the 3 grommets installed in the chassis with the High voltage and heater leads going
            through separate grommets.  Bolt the transformer in place with the supplied 8-32 bolts & Keps
            nuts.

            Install the Output transformer.  The Output transformer lies down along it’s ‘short axis’. Braid the
            High voltage leads together (Brown – Red – Blue) and also braid the secondary winding leads
            (Yellow (4 ohm), Green (8), Orange (16) Black (Common).


                                       TrinityAmps TRIWATT Builders Guide Ver. 2.31.docx- 31 -